We were tasked with replacing the old Crowd Barrier right the pitch for Cammell Laird FC.
The job itself was tricky as we obviously could not walk on the pitch, and there was limited access for any plant or machinery & the distribution of materials
We issued the clud with a proposed Method Statement of how we intended to carry the works of, which was agreed
We proposed to install a new Mesh Rebound System which consisted of a twin wire mesh panel and top rail for the spectators to safely lean on